Transcript
AS PER CONTRACT Item
Description
Unit
Quantity
Rate
Amount
PART - 6 LIGHTING AND ELECTRICAL DISTRIBUTION WORKS Section 6.8 - Street Lighting Work Supply and Install Road Lighting and Luminaries complete including brackets, lanterns, lamps, cut-outs, flexible cable and termination, winch system, grouting to base plate, foundation, accessories and commissioning as specified on drawings and specifications
6.8.1
30.5M High Mast complete for 4xI000W
No
100
39,516.00
3,951,600.00
6.8.2
30.5M High Mast complete for 6xI000W
No
30
44,084.00
1,322,520.00
Lanterns and Lamps
6.8.4
Supply and Install Lanterns and Lamps for 1000W High Pressure Sodium, cut-off, type V, Max Candela 55 deg. and with symmetrical distribution pattern (Installation included in items 6.8.1 & 6.8.2)
No
322
1,770.00
569,940.00
6.8.5
Supply and Install Lanterns and Lamps for 1000W High Pressure Sodium, cut-off, type V and with asymmetrical distribution pattern (Installation included in items 6.8.1 & 6.8.2)
No
258
1,770.00
456,660.00
6.8.6
Supply and Install Ceiling Mounted Flood Light under bridge with 150W High Pressure Sodium Lamps (Supply & installation complete with accessories included)
No
84
3,916.00
328,944.00
6.8.6a
Laying of Conduit work (15% of Total Rate)
No
134
587.40
78,711.60
Section 6.8 Total Carried Forward
Main Contractor -
Larsen and Toubro Limited
Page 1 of 7 254607073.xlsx.ms_office_BOQ
6,629,664.00
Sub Contractor -
Danway EME
AS PER CONTRACT Item
Description
Unit
Quantity
Rate
Amount
Total Brought to Forward
6,629,664.00
PART - 6 LIGHTING AND ELECTRICAL DISTRIBUTION WORKS (Cont'd) 6.8.7
Supply and Install Vehicular Underpass Lighting System excluding Ceiling mounted Flood Light for Underpass D1.1 with 150W High Pressure Sodium Lamps (Supply & installation complete with accessories included)
No
8
3,283.00
26,264.00
6.8.7a
Laying of Conduit work (15% of Total Rate)
No
14
492.45
6,894.30
6.8.8
Supply and Install Lighting System Complete for Each Overhead Gantry Signs (Power supply cables measured in item 6.8.15)
No
5
33,563.00
167,815.00
Supply Spare Lanterns and Lamps 6.8.9
Lantern 1000W High Pressure Sodium, cut-off, type V, Max Candela 55 deg. and with symmetrical distribution pattern
No
10
1,770.00
17,700.00
6.8.10
Lantern 1000W High Pressure Sodium, cut-off, type V, with asymmetrical distribution pattern
No
10
1,770.00
17,700.00
6.8.11
Lantern 150W HPSL
No
10
1,418.00
14,180.00
Section 6.8 Total Carried Forward
Main Contractor -
Larsen and Toubro Limited
Page 2 of 7 254607073.xlsx.ms_office_BOQ
6,873,323.00
Sub Contractor -
Danway EME
AS PER CONTRACT Item
Description
Unit
Quantity
Rate
Amount
Total Brought to Forward
6,873,323.00
PART - 6 LIGHTING AND ELECTRICAL DISTRIBUTION WORKS (Cont'd) Ducts UPVC Cable Road Crossings ducts laid and jointed in trench including end caps, draw chords, warning tape and duct markers as per specifications and as shown on drawings
Lighting Control Cabinet 6.8.13
Supply and Install 6-way control cabinet including excavation, backfilling all complete as per specifications and as shown on drawings
No
13
13,577.00
176,501.00
Item
1
91,218.00
91,218.00
m
12798
80.00
1,023,840.00
Earthing 6.8.14
Supply and Install earthing system to the whole street lighting network, including light poles, feeder pillar, control cabinet, etc. complete with earth pits, earth rods and the like (considered as shown in street light drawings)
Cables for Street Lighting Supply and Install the following Cables in trench including excavation and backfilling of trench and warning tapes, termination and commissioning complete as per specifications and as shown on drawings
6.8.15
2
4Cx25mm XLPE/SWA/PVC Copper Cable
Section 6.8 Total Carried Forward to Summary
Main Contractor -
Larsen and Toubro Limited
Page 3 of 7 254607073.xlsx.ms_office_BOQ
8,164,882.00
Sub Contractor -
Danway EME
AS PER CONTRACT Item
Description
Unit
Quantity
Rate
Amount
PART - 6 LIGHTING AND ELECTRICAL DISTRIBUTION WORKS (Cont'd)
Section 6.9 - Power (11kV) System
Cables and Ducts 11kV XLPE/SWA/PVC Cable including earth wire pulled in cable sleeves, including ducting, excavation, backfilling surround, warning tapes, and any other accessories in accordance with drawings and specifications 6.9.2
6.9.3
Main Contractor -
2
3 Core, 300mm XLPE Cable Supply - 3 Core, 300mm2 XLPE Cable Laying - 3 Core, 300mm2 XLPE Cable
m m
2,219 2,219
551.00 47.00
1,222,669.00 104,293.00
Fibre Optic Cable in 100mm PVC Duct Supply - Fibre Optic Cable Laying - Fibre Optic Cable
m m
2,219 2,219
36.00 12.00
79,884.00 26,628.00
Section 6.9 Total Carried Forward
1,433,474.00
Larsen and Toubro Limited
Page 4 of 7 254607073.xlsx.ms_office_BOQ
Sub Contractor -
Danway EME
AS PER CONTRACT Item
Description
Unit
Quantity
Rate
Amount
Total Brought to Forward
1,433,474.00
PART - 6 LIGHTING AND ELECTRICAL DISTRIBUTION WORKS (Cont'd) Substation Works 6.9.6
Furnish and Install 500 KVA, 11/0.4 KV Package unit substation including Oil Type Transformer, RMU, LV Switchgear, cables and other accessories in accordance with drawings and specifications. (DMS not included)
No
1
264,648.00
264,648.00
6.9.7
Relocate the existing 11/0.4 KV substation in accordance with drawings and specifications and as directed by the ADDC engineer (Only existing material used)
No
3
173,037.00
57,679.00
Section 6.9 Total Carried Forward to Summary
1,871,159.00
Section 6.10 -Power(400V) Network
Cables and Ducts 400V XLPE/SWA/PVC Cable including earth wire pulled in cable sleeves, including ducting, excavation, backfilling sorround, warning tapes, and any other accessories in accordance with drawings and specifications 6.10.2
6.10.3
6.10.4
2
4Cx70mm XLPE/SWA/PVC Copper Cable Supply - 4Cx70mm2 XLPE/SWA/PVC Copper Cable
m
1,061
137.00
145,357.00
Laying - 4Cx70mm2 XLPE/SWA/PVC Copper Cable
m
1,061
24.00
25,464.00
4Cx120mm XLPE/SWA/PVC Copper Cable Supply - 4Cx120mm2 XLPE/SWA/PVC Copper Cable
m
823
235.00
193,405.00
Laying - 4Cx120mm2 XLPE/SWA/PVC Copper Cable
m
823
30.00
24,690.00
2
2
-
4Cx240mm XLPE/SWA/PVC Copper Cable Supply - 4Cx240mm2 XLPE/SWA/PVC Copper Cable
m
823
461.00
379,403.00
m
823
41.00
33,743.00
Section 6.10 Total Carried Forward
802,062.00
Laying - 4Cx240mm2 XLPE/SWA/PVC Copper Cable
Main Contractor -
Larsen and Toubro Limited
Page 5 of 7 254607073.xlsx.ms_office_BOQ
Sub Contractor -
Danway EME
AS PER CONTRACT Item
Description
Unit
Quantity
Rate
Amount
Total Brought to Forward
802,062.00
PART - 6 LIGHTING AND ELECTRICAL DISTRIBUTION WORKS (Cont'd) LV Feeder Pillar 6.10.5
6.10.6
Supply and Install Street Lighting Feeder Pillar with accessories including concrete foundations, e xcavation, anchor bolts, complete in accordance with drawings and specifications
No
6
12,696.00
76,176.00
No
9
12,470.00
112,230.00
LV Service Cabinet Supply and Install LV Service Cabinet including excavation, backfilling all complete in accordance with drawings and specifications
Section 6.10 Total Carried Forward to Summary
990,468.00
Section 6.11 -Existing Works: 6.11.1
6.11.2
Remove, Salvage Existing 30.5M Light Poles complete with all Lanterns, Foundations, Cables, Cable Tiles, Control Cabinets and all associated equipment and transport it to ADDC store or as directed by ADDC as shown in the specifications.
Remove, Salvage Existing Lighting Control Cabinets, Feeder Pillars, Service Turret, including foundations and any associated equipment and transport it to ADDC store or as directed by ADDC as shown in the specifications.
No
100
4,435.00
443,500.00
No
15
1,034.00
15,510.00
Section 6.11 Total Carried Forward
Main Contractor -
Larsen and Toubro Limited
Page 6 of 7 254607073.xlsx.ms_office_BOQ
459,010.00
Sub Contractor -
Danway EME
AS PER CONTRACT Item
Description
Unit
Quantity
Rate
Amount
Total Brought to Forward
459,010.00
PART- 6 LIGHTING AND ELECTRICAL DISTRIBUTION WORKS (Cont'd) Remove, Salvage Existing POLE-MOUNTED 11/0.4kV Transformer substation and any associated equipment by ADDC as shown in the specifications.
No
10
17,734.00
177,340.00
6.11.4
Remove and Salvage Existing HV Cable
m
2,000
20.00
40,000.00
6.11.5
Remove and Salvage Existing MV/LV Cable
m
1,500
15.00
22,500.00
6.11.7
Raising or Lowering Existing MV/LV Cable
m
1,000
15.00
15,000.00
6.11.8
Raising or Lowering Existing HV Cable
m
800
20.00
16,000.00
6.11.9
Divert 11kV OHL as shown in the Drawing
m
1,000
396.00
396,000.00
6.11.3
Section 6.11 Total Carried Forward to Summary
Main Contractor -
Larsen and Toubro Limited
Page 7 of 7 254607073.xlsx.ms_office_BOQ
1,125,850.00
Sub Contractor -
Danway EME